Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.500 | 0.000 |
125W347 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के पत्र संख्या 240(1)/।।।(2)/21-8(सामान्य)/2019 दिनांक 15.02.2021
TS Amount (lakhs) : 306.42 Lacs
Financial Detail
Sanction Cost : 306.42 Lacs
Resanction Cost : 306.42 Lacs
Exp. Upto Last Fy : 253.37 Lacs
For CFY 2024-2025
Remaining : 53.05 Lacs
Demand : 40.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 253.37 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 80 %
Sanction on :
3 years 3 months ago
15 Feb 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उच्चाधिकारियों के अनुमोदन प्राप्त कर 0.500 कि0मी0 लम्बाई में निविदा आमंत्रित कर अवशेष भाग पर मोटर मार्ग की बचत से कार्य किया जा रहा है। -- as on 02-May-2024
Physical Peramenters