Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
125W374 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3579(1)/।।।(2)/21-39(एम0एल0ए0)/2017टी0सी0-3 दिनांक 10.09.2021
TS Amount (lakhs) : 303.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
303.10
Resanction Cost :
314.86
Tentative Cost :
303.10
Saving
11.76
Exp. Upto Last Fy : 302.96
For CFY 2024-2025
Remaining : 11.90
Demand : 2.00
Allotment : 13.19
Exp in CFY : 0.00
Total Up to Date Exp : 302.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
1 year 2 months ago
22 Apr 2023
Actual Completion Date:
1 year 2 months ago
22 Apr 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Physical Peramenters