Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
125W388 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6008/।।।(2)/21-39 (एम0एल0ए0)/2017 दिनांक 11.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
158.65
Resanction Cost :
158.65
Tentative Cost :
158.65
Exp. Upto Last Fy : 142.75
For CFY 2024-2025
Remaining : 15.90
Demand : 5.00
Allotment : 15.90
Exp in CFY : 0.00
Total Up to Date Exp : 142.75
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
11 Dec 2021
Tentative Completion date:
1 year 1 month ago
15 Jun 2023
Actual Completion Date:
1 year 1 month ago
15 Jun 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Physical Peramenters