Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
125W516 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ।/4085/2023 ई पत्रावली संख्या 38302 दिनांक 25.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 218.65 Lacs
Resanction Cost : 218.65 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 218.65 Lacs
Demand : 150.00 Lacs
Allotment : 10.76 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 35 %
Sanction on :
6 months 3 weeks ago
25 Oct 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters