Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
125W527 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 73530/2023 ई-पत्रावली संख्या 27563 दिनांक 07.12.2023
TS Amount (lakhs) : 382.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
382.15
Resanction Cost :
382.15
Tentative Cost :
382.15
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 382.15
Demand : 250.00
Allotment : 51.00
Exp in CFY : 50.45
Total Up to Date Exp : 50.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
1 year 5 days ago
12 Jul 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024