Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.075 | 1.075 | 0.000 | 1.075 | 1.070 | 0.000 |
125W535 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7197904/2024 E-Patrawali No 36086
TS Amount (lakhs) : 100.18 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
100.18
Resanction Cost :
100.18
Tentative Cost :
100.18
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 100.18
Demand : 80.00
Allotment : 7.50
Exp in CFY : 7.05
Total Up to Date Exp : 7.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 5 days ago
12 Mar 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर । -- as on 25-Jun-2024
Physical Peramenters