Work Profile Report [125W601]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली सं0 27563 दिनांक 01.10.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
114.46
Resanction Cost :
114.46
Tentative Cost :
114.46
Exp. Upto Last Fy :
41.54
For CFY 2025-2026
Remaining :
72.92
Demand :
60.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
41.54
Construction Started
Sanction on : 7 months 2 weeks ago
01 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
70 %
Tentative Completion date on : 3 weeks 6 days from now
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 17-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: