Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
126W134 :
Administrative Approval Detail : शासनादेश संख्या 2181 (1)/।।। (2)/20-06 (एम॰एल॰ए॰)/2017. टी॰सी॰। दिनांक 07.12.2020
TS Amount (lakhs) : 853.16 Lacs
Financial Detail
Sanction Cost : 853.16 Lacs
Resanction Cost : 853.16 Lacs
Exp. Upto Last Fy : 811.40 Lacs
For CFY 2024-2025
Remaining : 41.76 Lacs
Demand : 15.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 811.40 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 5 months ago
07 Dec 2020
Tentative Completion date:
8 months 4 weeks ago
20 Aug 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।दायित्व शेष। -- as on 12-Sep-2023
Physical Peramenters