Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
126W176 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : अपर सचिव, उत्तराखण्ड़ शासन के ई॰ फाईल सं॰ 49189 दि॰ 19.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.70
Resanction Cost :
14.70
Tentative Cost :
14.70
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 14.60
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.19
Total Up to Date Exp : 0.29
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 10 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इस कार्यालय पत्रांक 480/1सी0 दिनांक 24.04.2024 द्वारा समरेखण प्रस्ताव अधीक्षण अभियन्ता गोपेश्वर को प्रेषित। जिसके क्रम में अधीक्षण अभियन्ता गोपेश्वर के कार्यालय पत्रांक 1822/625 याता0-07/24 दिनांक 15.05.2024 द्वारा समरेखण अनुमोदित। -- as on 03-Jun-2024
Physical Peramenters