Work Profile Report [126W220]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई॰ पत्रावली सं॰ 74390 दि॰ 22.11.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
73.09
Resanction Cost :
73.09
Tentative Cost :
73.09
Exp. Upto Last Fy :
21.54
For CFY 2025-2026
Remaining :
51.55
Demand :
39.30
Allotment :
36.74
Exp in CFY :
36.74
Total Up to Date Exp :
58.28
Construction Started
Sanction on : 1 year 3 weeks ago
22 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 week from now
25 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 05-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: