Work Profile Report [126W221]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई0पत्रावली संख्या 52001 दि॰ 01.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.55
Resanction Cost :
91.55
Tentative Cost :
91.55
Exp. Upto Last Fy :
0.16
For CFY 2025-2026
Remaining :
91.39
Demand :
85.00
Allotment :
84.88
Exp in CFY :
84.88
Total Up to Date Exp :
85.04
Construction Started
Sanction on : 11 months 2 weeks ago
01 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
88 %
Tentative Completion date on : 2 months 2 weeks from now
03 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3 km लंबाई मैं P C का कार्य पूर्ण। शेष कार्य (कॉजवे एवम दीवार) प्रगति पर । -- as on 07-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: