Work Profile Report [126W222]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई0पत्रावली संख्या 74934 दि॰ 01.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
217.98
Resanction Cost :
217.98
Tentative Cost :
217.98
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
217.88
Demand :
195.00
Allotment :
66.00
Exp in CFY :
65.94
Total Up to Date Exp :
66.04
Construction Started
Sanction on : 7 months 1 week ago
01 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
47 %
Tentative Completion date on : 10 months 2 weeks from now
29 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 01-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: