Work Profile Report [126W223]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : सयुक्त सचिव उत्तराखण्ड शासन के इ॰पत्रावली सं0 49189 दि0 27.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
265.66
Resanction Cost :
265.66
Tentative Cost :
265.66
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
265.56
Demand :
80.40
Allotment :
76.70
Exp in CFY :
31.89
Total Up to Date Exp :
31.98
Construction Started
Sanction on : 11 months 3 weeks ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
12 %
Tentative Completion date on : 9 months 2 weeks from now
12 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.425 किमी0 लम्बाई के सापेक्ष 1.50 किमी0 लम्बाई में जी-1 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: