Work Profile Report [126W224]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : अनु सचिव उत्तराखण्ड शासन के ई0पत्रावली 46275/06 दि0 06.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
403.41
Resanction Cost :
403.41
Tentative Cost :
403.41
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
403.31
Demand :
220.00
Allotment :
68.77
Exp in CFY :
18.51
Total Up to Date Exp :
18.61
Construction Started
Sanction on : 5 months 2 days ago
06 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
6 %
Tentative Completion date on : 1 year 4 months from now
15 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand