Work Profile Report : 126W224
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : अनु सचिव उत्तराखण्ड शासन के ई0पत्रावली 46275/06 दि0 06.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
403.41
Resanction Cost :
403.41
Tentative Cost :
403.40
Saving
0.01
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
403.31
Demand :
200.00
Allotment :
143.17
Exp in CFY :
143.17
Total Up to Date Exp :
143.27
Construction Started
Sanction on : 11 months 6 days ago
06 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
38 %
Tentative Completion date on : 10 months 2 days from now
15 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
5.50 किमी0 लम्बाई के सापेक्ष 4.00 किमी0 लम्बाई में जी-1 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 31-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: