Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 30 | 48 | 48 | 0 |
126W9 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6970/111 (2)/13-40 (प्रा.आ.)/2013 दिनांक 14/12/2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.38
Resanction Cost :
31.38
Tentative Cost :
31.38
Exp. Upto Last Fy : 14.57
For CFY 2024-2025
Remaining : 16.81
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 14.57
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
10 years 7 months ago
14 Dec 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
उत्तराखण्ड शासन के ई0 पत्रावली सख्या 52001, दिनांक 08.05.2024 द्वारा आगणन आपत्तियों में प्राप्त। आपत्तियों के निराकरण की कार्यवाही खण्ड स्तर पर गतिमान है। -- as on 03-Jun-2024
Physical Peramenters