Work Profile Report [126W91]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 403/।।।(2)/17-06(एम0एल0ए0)/2017 दिनांक 25.07.2017
TS Amount (lakhs) : 309.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
309.91
Resanction Cost :
309.91
Tentative Cost :
309.91
Exp. Upto Last Fy :
56.67
For CFY 2024-2025
Remaining :
253.24
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
56.67
Construction Started
Sanction on : 7 years 3 months ago
25 Jul 2017
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
70 %
Tentative Completion date on : 3 years 4 months ago
30 Jun 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 04 एवं 05 में विवाद सुलझाने के उपरान्त, कार्य प्रगति पर। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand