Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 2.700 | 3.3 | 1.300 | 0.000 |
126W91 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 403/।।।(2)/17-06(एम0एल0ए0)/2017 दिनांक 25.07.2017
TS Amount (lakhs) : 309.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
309.91
Resanction Cost :
309.91
Tentative Cost :
309.91
Exp. Upto Last Fy : 56.67
For CFY 2024-2025
Remaining : 253.24
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 56.67
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
6 years 11 months ago
25 Jul 2017
Tentative Completion date:
3 years 2 weeks ago
30 Jun 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
मोटर मार्ग केे प्रथम 4.00 किमी॰ लम्बाई में पहाड़ कटान का कार्य पूर्ण। लक्षित ग्राम के सापेक्ष कि0मी0 04 में महरगांव जोडा जा चुका है। किन्तु किमी0 5 एवं 06 में ग्रामवासियों द्वारा समरेखण विवाद किया जा रहा है। विवाद सुलझाने हेतु माननीय विधायक कर्णप्रयाग विधान सभा क्षेत्र एवं अन्य जनप्रतिनिधियों द्वारा भी कई बार प्रयास किये गये परन्तु ग्रामीणों का विवाद वर्तमान समय तक भी बना हुआ है।
उक्त मोटर मार्ग में कि0मी0 04 तक डामरीकरण का कार्य पी॰एम॰जी॰एस॰वाई॰ कर्णप्रयाग के अन्तर्गत स्वीकृत है।
-- as on 15-Dec-2023
Physical Peramenters