Work Profile Report [127W150]
Forest
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 77131/I/267156/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
572.04
Resanction Cost :
572.04
Tentative Cost :
572.04
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
572.04
Demand :
422.04
Allotment :
369.34
Exp in CFY :
369.34
Total Up to Date Exp :
369.34
Construction Started
Sanction on : 9 months 3 weeks ago
09 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 3 weeks 6 days from now
01 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in Progress. -- as on 13-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: