Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
128W184 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 928/(1)।।।(2)/21-04(एम0एल0ए0)/2017 दिनांक 30.03.2021
TS Amount (lakhs) : 74.18 Lacs
Financial Detail
Sanction Cost : 74.18 Lacs
Resanction Cost : 74.18 Lacs
Exp. Upto Last Fy : 57.76 Lacs
For CFY 2024-2025
Remaining : 16.42 Lacs
Demand : 8.00 Lacs
Allotment : 1.64 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 57.76 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
30 Mar 2021
Tentative Completion date:
2 months 3 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य पूर्ण। अनुरक्षण मद के अन्तर्गत कार्य किया जाना है। -- as on 16-Apr-2024
Physical Peramenters