Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 95 | 95 | 0.000 | 95 | 0.000 | 0.000 |
128W224 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण विभाग अनुभाग-2 की ई फाईल सं0 49537 दिनांक 21.03.2023
TS Amount (lakhs) : 19.95 Lacs
Financial Detail
Sanction Cost : 19.95 Lacs
Resanction Cost : 19.95 Lacs
Exp. Upto Last Fy : 11.53 Lacs
For CFY 2024-2025
Remaining : 8.42 Lacs
Demand : 8.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 11.53 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 1 month ago
21 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
1 month 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
सेतुओं का स्थल चयन,जियो टेक्निकल एवं ड्राफ्ट डिजाइन डी0पी0आर0 का कार्य पूर्ण। सेतुओं के डिजाइन का कार्य गतिमान। इस कार्यालय के पत्र सं0 703/15सी0 दिनांक 22.03.2024 द्वारा सेतु निर्माण से प्रभावित होने वाले वन भूमि की संयुक्त निरीक्षण की तिथि निर्धारित करने हेतु डी0एफ0ओ0 को पत्र प्रेषित किया गया है। -- as on 15-Apr-2024
Physical Peramenters