Work Profile Report [128W249]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश संख्या 4088/।।।(2)/2023-(प्रा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
257.12
Resanction Cost :
257.12
Tentative Cost :
257.12
Exp. Upto Last Fy :
172.20
For CFY 2024-2025
Remaining :
84.92
Demand :
84.92
Allotment :
84.00
Exp in CFY :
7.55
Total Up to Date Exp :
179.75
Construction Started
Sanction on : 1 year 3 weeks ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
70 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 02-Mar-2024