Work Profile Report : 128W25

जनपद चमोली में चांदनीखाल- रड़वा-काण्डई-रेंसू मोटर मार्ग का विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0ः-543 /।।।(2)/09-14 (प्रा0आ0)/08 दिनांक 11.02.2009

TS Amount (lakhs) : 220.03 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

220.50

Resanction Cost :

220.50

Tentative Cost :

220.50

Exp. Upto Last Fy :

1.83

For CFY 2025-2026

Remaining :

218.67

Demand :

20.00

Allotment :

20.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.83

Construction Started

Sanction on : 17 years 1 day ago

11 Feb 2009

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

25 %

Tentative Completion date on : 2 years 1 month from now

31 Mar 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
3.75
3.75
-

Remark

view all

पहाड़ कटान कार्य प्रगति में । -- as on 02-Feb-2026

Rating : 32

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: