Work Profile Report [128W89]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0ः- 543/।।।(2)/09-14(प्रा0आ0)/08 दिनांक 11.02.2009
TS Amount (lakhs) : 183.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
183.75
Resanction Cost :
183.75
Tentative Cost :
183.75
Exp. Upto Last Fy :
179.68
For CFY 2024-2025
Remaining :
4.07
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
179.68
Work completed
Sanction on : 15 years 10 months ago
11 Feb 2009
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-May-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: R.C.C Bridle Bridge Over Sarnha Gadhera