Work Profile Report [129W527]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शा0सं0 313/।।।(2)/21-34(एम.एल.ए.)2017टीसीआई दिनांक 26.02.2021
TS Amount (lakhs) : 86.13 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.13
Resanction Cost :
86.13
Tentative Cost :
65.00
Saving
21.13
Exp. Upto Last Fy :
54.68
For CFY 2024-2025
Remaining :
31.45
Demand :
1.29
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
54.68
In Maintenance After Completion
Sanction on : 3 years 9 months ago
26 Feb 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
30 Mar 2022
Actual Completion Date : 2 years 8 months ago
30 Mar 2022
Physical Linear Components
Remark
Overall Saving 21.13 has been recorded as expected cost of work reduced from 86.13 to 65.00 . Due to Tender Below Rate. -- as on 06-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand