Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.500 | 0 | 0.000 | 0.000 |
129W600 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. Order No. 2619/(1)/III(2)/21-32(MLA)/2017 T.C Dt. 10.08.2021
TS Amount (lakhs) : 116.17 Lacs
Financial Detail
Sanction Cost : 116.17 Lacs
Resanction Cost : 123.80 Lacs
Exp. Upto Last Fy : 70.45 Lacs
For CFY 2024-2025
Remaining : 53.35 Lacs
Demand : 0.60 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 70.45 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
10 Aug 2021
Tentative Completion date:
2 weeks 5 days ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व अवशेष -- as on 30-Apr-2024
Physical Peramenters