Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.2 | 5.2 | 0.000 | 5.2 | 5.200 | 0.000 |
129W650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-48594, लोक निर्माण अनुभाग-2 दिनांक 14.03.2023
TS Amount (lakhs) : 811.99 Lacs
Financial Detail
Sanction Cost : 811.99 Lacs
Resanction Cost : 872.90 Lacs
Exp. Upto Last Fy : 323.13 Lacs
For CFY 2024-2025
Remaining : 549.77 Lacs
Demand : 400.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 323.13 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 27 %
Up to Date : 27 %
Sanction on :
1 year 2 months ago
14 Mar 2023
Tentative Completion date:
4 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग में WBM का कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters