Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.2 | 5.2 | 0.000 | 5.2 | 5.200 | 4.100 |
129W650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-48594, लोक निर्माण अनुभाग-2 दिनांक 14.03.2023
TS Amount (lakhs) : 811.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
811.99
Resanction Cost :
872.90
Tentative Cost :
872.90
Exp. Upto Last Fy : 323.13
For CFY 2024-2025
Remaining : 549.77
Demand : 490.00
Allotment : 221.92
Exp in CFY : 195.27
Total Up to Date Exp : 518.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 27 %
Up to Date : 70 %
Sanction on :
1 year 4 months ago
14 Mar 2023
Tentative Completion date:
2 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर चैडीकरण एवं क्रास डेªनेज व डी.बी.एम. व बी.सी. का कार्य 4.100 किमी0 में पूर्ण, शेष 1.100 किमी0 ल0 में काष्तकारों के आपसी भूमि विवाद के कारण कार्य मंें व्यवधान था, जिसके समाधान हेतु दिनांक 28.06.2024 को उपजिलाधिकारी, लक्सर द्वारा कार्यस्थल पर उपस्थित होकर निषानदेही का कार्य करवाया गया। जिसके उपरान्त जी0एस0बी0 का कार्य प्रगति पर है। -- as on 30-Jun-2024
Physical Peramenters