Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.200 | 0 | 0.000 | 0.000 |
129W654 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 35.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.02
Resanction Cost :
37.65
Tentative Cost :
37.65
Exp. Upto Last Fy : 19.81
For CFY 2024-2025
Remaining : 17.84
Demand : 0.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.81
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
8 months 2 weeks ago
01 Nov 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। 12/2023 दायित्व शेष -- as on 12-Jan-2024
Physical Peramenters