Work Profile Report [129W664]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-49430, लोक निर्माण अनुभाग-2 दिनांक 25.03.2023
TS Amount (lakhs) : 66.66 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.66
Resanction Cost :
66.66
Tentative Cost :
60.00
Saving
6.66
Exp. Upto Last Fy :
45.53
For CFY 2024-2025
Remaining :
21.13
Demand :
10.39
Allotment :
17.45
Exp in CFY :
4.94
Total Up to Date Exp :
50.47
In Maintenance After Completion
Sanction on : 1 year 7 months ago
25 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 4 weeks ago
26 Dec 2023
Actual Completion Date : 10 months 3 weeks ago
30 Dec 2023
Physical Linear Components
Remark
Overall Saving 6.66 has been recorded as expected cost of work reduced from 66.66 to 60.00 . -- as on 06-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: