Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
12W151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1440/।।।-(2)/11-05 (प्र्रा0आ0)/2010 दिनांक 26.03.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 63.00 Lacs
Resanction Cost : 63.00 Lacs
Exp. Upto Last Fy : 0.24 Lacs
For CFY 2024-2025
Remaining : 62.76 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
2 years 4 months ago
30 Dec 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
क्षतिपूरक वृक्षारोपण हेतु भूमि का वन विभाग के नाम हस्तान्तरण एवं नामान्तरण आदेश पारित करने हेतु पत्रांक 884/ 8 सी0 दि0 08.05.2024 द्वारा जिलाधिकारी नैनीताल को पत्र लिखा गया है। -- as on 13-May-2024
Physical Peramenters