Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
12W151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1440/।।।-(2)/11-05 (प्र्रा0आ0)/2010 दिनांक 26.03.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy : 0.24
For CFY 2024-2025
Remaining : 62.76
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
13 years 3 months ago
28 Mar 2011
Tentative Completion date:
2 years 6 months ago
30 Dec 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
पुनः इस कार्यालय के पत्रांक 1055/ 8 सी0 दि0 04.06.2024 को जिलाधिकारी नैनीताल को पत्र लिखा गया है। जिलाधिकारी नैनीताल द्वारा दि0 05.06.2024 को उपजिलाधिकारी कोश्यां कुटौली को चयनित भूमि के प्रस्ताव उपलब्ध कराने हेतु निर्देशित किया गया है। -- as on 07-Jun-2024
Physical Peramenters