Work Profile Report [12W151]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1440/।।।-(2)/11-05 (प्र्रा0आ0)/2010 दिनांक 26.03.2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy :
0.24
For CFY 2025-2026
Remaining :
62.76
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.24
Construction Started
Sanction on : 14 years 1 month ago
28 Mar 2011
Physical Progress:
At start of FY 2025-2026 :
26 %
Up to Date :
26 %
Tentative Completion date on : 4 weeks 13 hours ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जिलाधिकारी द्वारा नामान्तरण ध्हस्तान्तरण के आदेश दिनांक 10.02.2025 द्वारा प्राप्त। अग्रिम कार्यवाही गतिमान। -- as on 14-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand