Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
12W244 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2212/।।।(2)/15-11(प्रा0आ0)/2015 दिनांक 30.03.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 46.80 Lacs
Resanction Cost : 46.80 Lacs
Exp. Upto Last Fy : 7.50 Lacs
For CFY 2024-2025
Remaining : 39.30 Lacs
Demand : 35.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.50 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 1 month ago
30 Mar 2015
Tentative Completion date:
2 years 7 months ago
30 Sep 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
विधिवत स्वीकृति प्राप्त करने हेतु इस कार्यालय के पत्रांक 109/8 सी0 दिनांक 15.01.2022 द्वारा सैद्वान्तिक स्वीकृति की अनुपालन आख्या प्रभागीय वनाधिकारी नैनीताल को प्रेषित। -- as on 16-May-2024
Physical Peramenters