Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 30 | 30 | 30 | 0 |
12W305 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2511/।।।(2)/16-57(प्रा0आ0)/2015 दिनांक 27.09.2016
TS Amount (lakhs) : 4.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.40
Resanction Cost :
4.40
Tentative Cost :
4.40
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 4.40
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 9 months ago
27 Sep 2016
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण अनुमोदित। ग्रामवासियों द्वारा अब समरेखण में विवाद किया जा रहा है। दिनांक 22.03.19 को समरेखन का पुनः निरीक्षण किया गया, ग्रामीणों द्वारा अनापत्ति प्रमाण पत्र नहीं दिया जा रहा है। अनापत्ति प्रमाण पत्र प्राप्त किये जाने हेतु सहा0 अभि0 तृतीय के पत्रांक 252/ 12 सी0 दि0 12.07.22 द्वारा ग्राम प्रधान को पत्र प्रेषित है। एवं प्रति मा0 विधायक जी को प्रेषित है। -- as on 22-Jun-2023
Physical Peramenters