Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
12W363 :
Administrative Approval Detail : शासनादेश सं0 2806/।।।(2)/17-57 (एम0एल0ए0)/2017 दिनांक 13.10.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.13
Resanction Cost :
20.13
Tentative Cost :
20.13
Exp. Upto Last Fy : 1.18
For CFY 2024-2025
Remaining : 18.95
Demand : 18.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.18
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 9 months ago
13 Oct 2017
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण स्टेज-1 2.00 किमी0 लम्बाई हेतु स्वीकृति प्राप्त।प्रतिकर प्रस्ताव गठित किया जा रहा है। -- as on 02-Apr-2024