Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
12W376 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0दे0स0 1318/।।। (2)/18-57 (एम0एल0ए0)/2017 दि0 21.03.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
38.60
Resanction Cost :
38.60
Tentative Cost :
38.60
Exp. Upto Last Fy : 3.37
For CFY 2024-2025
Remaining : 35.23
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 3 months ago
21 Mar 2018
Tentative Completion date:
2 years 9 months ago
30 Sep 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 प्रमुख सचिव, लो0नि0वि0 देहरादून को मु0 अभि0 हल्द्वानी के पत्रांक 2547/12 याता0-ह0/2020 दि0 25.06.2021 द्वारा रू0 114.00 लाख की प्रेषित। -- as on 21-Aug-2023
Physical Peramenters