Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 | ||
Span of Bridges [m] | 48 | 48 | 48 | 0 |
12W379 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0दे0 सं0 1710/।।।(2)/18-57(एम0एल0ए0)/2017 दि0 02.05.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.75
Resanction Cost :
49.75
Tentative Cost :
49.75
Exp. Upto Last Fy : 0.14
For CFY 2024-2025
Remaining : 49.61
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.14
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 years 2 months ago
02 May 2018
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
प्रभागीय वनाधिकारी नैनीताल द्वारा दि0 29.05.2024 को आपत्तियों में प्राप्त, -- as on 04-Jun-2024
Physical Peramenters