Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.75 | 1.75 | 1.75 | 0 |
12W431 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1942/ ।।। (2)/20-57 (एम0एल0ए0) 2017 - टी0सी0-।। दिनांक 22.10.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1.63
Resanction Cost :
1.63
Tentative Cost :
1.63
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 1.53
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 80 %
Sanction on :
3 years 8 months ago
22 Oct 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
एफ0टी0आई0 हल्द्वानी से दि0 18.05.24 को गूगल मैप व सी0ए0 मैप तैयार कर लिये गये है, वन भूमि प्रस्ताव प्रतिहस्ताक्षर कराये जा रहे है। -- as on 04-Jun-2024
Physical Peramenters