Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.45 | 3.45 | 3.100 | 0.35 | 0.350 | 0.350 |
12W450 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल संख्या - 22351, दिनांक 27.07.2022
TS Amount (lakhs) : 42.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.13
Resanction Cost :
42.13
Tentative Cost :
42.13
Exp. Upto Last Fy : 25.87
For CFY 2024-2025
Remaining : 16.26
Demand : 15.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
1 year 2 months ago
30 Apr 2023
Actual Completion Date:
11 months 3 weeks ago
26 Jul 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा प्रस्ताव गठित। अवशेष धनराशि से प्रतिकर भुगतान हेतु समाचार पत्र के माध्यम से कास्तकारों को सूचना पे्रषित की गई है। -- as on 02-Apr-2024
Physical Peramenters