Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 22 | 22 | 22 | 0 |
12W468 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 47049 लोक निर्माण अनुभाग-2 देहरादून दिनांक 16.02.2023
TS Amount (lakhs) : 6.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.82
Resanction Cost :
6.82
Tentative Cost :
6.82
Exp. Upto Last Fy : 1.49
For CFY 2024-2025
Remaining : 5.33
Demand : 5.33
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.49
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 30 %
Sanction on :
1 year 5 months ago
16 Feb 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जि0ओ0 टेक्निकल परीक्षण, भूवैज्ञानिक निरीक्षण तथा स्थल चयन का कार्य पूर्ण। -- as on 02-Apr-2024
Physical Peramenters