Work Profile Report [12W628]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : ई-फाईल सं0 87905/57 लोक निर्माण अनुभाग-2 देहरादून दिनांक 04.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5.21
Resanction Cost :
5.21
Tentative Cost :
5.21
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
5.21
Demand :
1.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 4 months 1 week ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 5 months 2 weeks from now
30 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वे का कार्य पूर्ण, सेतु के साईट सलैक्शन की कार्यवाही गतिमान। -- as on 31-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: