Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
15W463 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2724/।।।(2)/15-05(मा0मु0म0घो0)/15 दिनांक 23/04/2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
70.92
Resanction Cost :
70.92
Tentative Cost :
70.92
Exp. Upto Last Fy : 2.95
For CFY 2024-2025
Remaining : 67.97
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 2 months ago
23 Apr 2015
Tentative Completion date:
4 years 7 months ago
13 Dec 2019
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 14: AIP Conservator
Bottelneck: no issue
प्रमुख अभियन्ता एंव विभागाध्यक्ष को एन0पी0वी0 की धनराशि के सम्बन्घ में पत्र प्रेषित है। पत्र संख्या 12/25 बजट (एन0पी0वी0/भूमि प्रतिकर रो0से0)/2023-24 दिनांक 24.05.2023 द्वारा प्राप्त सी0सी0एल0 के अनुसार एन0पी0वी0 की धनराशि जमा की जा चुकी है। -- as on 20-Feb-2024
Physical Peramenters