Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.65 | 1.65 | 0.000 | 1.65 | 0.000 | 0.000 |
15W752 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No 6021 /III(2)/21 -44 (M.L.A.)/2017 T.C. -III dt 14.12.2021
TS Amount (lakhs) : 112.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.29
Resanction Cost :
112.29
Tentative Cost :
112.29
Exp. Upto Last Fy : 51.32
For CFY 2024-2025
Remaining : 60.97
Demand : 43.90
Allotment : 0.00
Exp in CFY : 17.38
Total Up to Date Exp : 68.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 95 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Compensation Dispute
1.680 किमी0 में से 1.620 किमी0 कार्य पूर्ण -- as on 04-Jul-2024
Physical Peramenters