Work Profile Report : 15W782

राज्य योजना के अन्र्तगत सातसिलिंग थल मोटर मार्ग के किमी0 29 से चामू भण्डारी गांव रजवार तक मोटर मार्ग का नव निर्माण कार्य। (प्रथम चरण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 11/III(2)/17-48 (PE)/2016 Dated 04 January 2017

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

96.33

Resanction Cost :

96.33

Tentative Cost :

96.33

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

96.33

Demand :

3.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 9 years 2 months ago

04 Jan 2017

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 3 weeks from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
7
7
-
Jobs
1
1
1
-

Remark

view all

7.00 किमी की प्रथम चरण की स्वीकृति के सापेक्ष प्रथम 3.00 किमी का मुभावजा वितारित करने के प्रयास किये जा रहे है । किन्तु प्रभावित काश्तकारों का मुआवजा धनराशि कम होने एवं ग्रामवासिओं के पलायन के कारण काश्तकारों / ग्रामवासिओं द्वारा Interest नही लिया जा रहा है । ग्राम प्रधान एंव स्थानीय जनप्रतिनिधियों के साथ वार्ता कर मुआवजा भुगतान प्राप्त करने हेतु प्रयास किये जा रहे है। -- as on 17-Feb-2026

Rating : 127

Forest Case Pending At : 17: AIP Govt of India

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: