Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16 | 16 | 16 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
15W847 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन का पत्रांक संख्या-2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21 जुलाई, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
231.99
Resanction Cost :
231.99
Tentative Cost :
231.99
Exp. Upto Last Fy : 180.52
For CFY 2024-2025
Remaining : 51.47
Demand : 51.47
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 180.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 4 weeks ago
18 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष है । -- as on 06-Jun-2024
Physical Peramenters