Work Profile Report [15W870]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No. 51161
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.01
Resanction Cost :
189.01
Tentative Cost :
189.01
Exp. Upto Last Fy :
68.31
For CFY 2025-2026
Remaining :
120.70
Demand :
111.00
Allotment :
76.40
Exp in CFY :
75.75
Total Up to Date Exp :
144.06
Construction Started
Sanction on : 1 year 5 months ago
23 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
29 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, वित्तीय दायित्यो का भुगतान शेष -- as on 07-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand