Work Profile Report [15W875]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 66448 G.O. ltr No. 285/xxxvii(2)/24/09 Budget /2022, Nayak Anubhag-2 dt 26-02-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Building ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
451.26
Resanction Cost :
451.26
Tentative Cost :
451.26
Exp. Upto Last Fy :
158.25
For CFY 2025-2026
Remaining :
293.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
158.25
none
Sanction on : 1 year 6 months ago
26 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
70 %
Tentative Completion date on : 3 months 2 weeks from now
22 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाईल व रंग रोगन का कार्य प्रगति में। कार्य की भोतिक प्रगति लगभग 70 प्रतिशत है। -- as on 30-Aug-2025