Work Profile Report [16W105]

जनपद पिथौरागढ में विधानसभा क्षेत्र डीडीहाट के अन्तर्गत सुनाली से हरडकटिया तक मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0ंसं0 5423 (1)/।।।-(2)/10-18 (प्रा0आ0)/2010 दिनांक 27.8.2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

41.16

Resanction Cost :

41.16

Tentative Cost :

41.16

Exp. Upto Last Fy :

27.13

For CFY 2025-2026

Remaining :

14.03

Demand :

3.00

Allotment :

1.08

Exp in CFY :

1.08

Total Up to Date Exp :

28.21

Work completed

Sanction on : 15 years 3 months ago

27 Aug 2010

Physical Progress:

At start of FY 2025-2026 :

90 %

Up to Date :

90 %

Tentative Completion date on : 11 months 2 weeks from now

30 Nov 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000
Bridge
2 (48m)
2 (48m)
0 (0.000m)
2 (48m)
0 (0.000m)
0 (0.000m)

Remark

view all

प्रतिकर प्रस्ताव गठित भुगतान की कार्यवाही गतिमान। -- as on 29-Nov-2025

Rating : 90

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: