Length of Road [Km] | 6 | 6 | 6 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 |
16W266 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1730/।।।(2)/14-03(मु.मं.घो.)/2014 दिनांक 24.09.2014।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.26
Resanction Cost :
52.26
Tentative Cost :
52.26
Exp. Upto Last Fy : 5.44
For CFY 2024-2025
Remaining : 46.82
Demand : 18.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.44
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
9 years 9 months ago
24 Sep 2014
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। भमि प्रतिकर भुगतान अवशेष। -- as on 31-Jul-2020