Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
16W566 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3214/।।।(2)/21-42 (एम0एल0ए0)/2017 दि0 27.08.2021
TS Amount (lakhs) : 94.28 Lacs
Financial Detail
Sanction Cost : 94.28 Lacs
Resanction Cost : 94.28 Lacs
Exp. Upto Last Fy : 26.80 Lacs
For CFY 2024-2025
Remaining : 67.48 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 26.80 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
2 years 8 months ago
27 Aug 2021
Tentative Completion date:
1 year 4 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.30 कि0मी0 पहाड़ कटान का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 10-Apr-2024
Physical Peramenters