Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
16W651 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई फाईल संख्या 53524 दिनांक 18.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.94
Resanction Cost :
91.94
Tentative Cost :
91.94
Exp. Upto Last Fy : 15.96
For CFY 2024-2025
Remaining : 75.98
Demand : 50.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 15.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 30 %
Sanction on :
10 months 4 weeks ago
18 Aug 2023
Tentative Completion date:
1 month 3 weeks from now
10 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 16-Dec-2023
Physical Peramenters