Work Profile Report [16W652]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई फाईल संख्या 52192 दिनांक 19.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
103.34
Resanction Cost :
103.34
Tentative Cost :
103.34
Exp. Upto Last Fy :
98.11
For CFY 2025-2026
Remaining :
5.23
Demand :
2.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
98.11
In Maintenance After Completion
Sanction on : 2 years 4 months ago
19 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 2 weeks from now
30 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण।वर्तमान में कार्य तीन वषीर्य अनुरक्षण के अन्तर्गत है। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: