Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
16W652 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई फाईल संख्या 52192 दिनांक 19.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
103.34
Resanction Cost :
103.34
Tentative Cost :
103.34
Exp. Upto Last Fy : 19.22
For CFY 2024-2025
Remaining : 84.12
Demand : 75.00
Allotment : 10.87
Exp in CFY : 10.87
Total Up to Date Exp : 30.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 45 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
3 months 1 week from now
30 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग तथा इन्टरकोट का कार्य पूर्ण। शेष कार्य प्रगति पर -- as on 26-Jun-2024