Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
16W657 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या-52192 दिनांक 27 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
228.81
Resanction Cost :
228.81
Tentative Cost :
228.81
Exp. Upto Last Fy : 51.88
For CFY 2024-2025
Remaining : 176.93
Demand : 140.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 51.88
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 40 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
6 months 2 weeks from now
05 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 04-Mar-2024
Physical Peramenters