Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
17W341 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइल संख्या 36352 लोक निर्माण विभाग अनुभाग 2
TS Amount (lakhs) : 223.34 Lacs
Financial Detail
Sanction Cost : 223.34 Lacs
Resanction Cost : 223.34 Lacs
Exp. Upto Last Fy : 25.39 Lacs
For CFY 2024-2025
Remaining : 197.95 Lacs
Demand : 192.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.17 Lacs
Total Up to Date Exp : 25.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
4 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण का कार्य पूर्ण, जी1 एकत्रीकरण का कार्य प्रगति पर -- as on 20-Feb-2024
Physical Peramenters